South 5th Street Reconstruction Project

Project Summary:  Click here for South 5th Street Reconstruction Information

Project Timeline: April 2024 – October 2024

Project Updates:

4/26/2024 – Milling progress

4/18/2024 – Tree removal work has been started.  Clean-up will continue.

Timeline Plan (all work is weather permitting):

4/29/2024 – Temporary water will be set up

5/6/2024 – Underground work is scheduled

 